Ballast Nedam Infra B.V.

Location

Utrecht

Founded

1970-12-29

Risk Signals

515 news mentions monitored

Industry Context

This company is tracked across risk categories, including those related to its sector (e.g., Operative Builders, Heavy Construction, Not Elsewhere Classified, Refuse Systems, Engineering Services), including supply chain integrity, ESG practices, labor disputes, and regulatory compliance.

Recent Articles about Ballast Nedam Infra B.V.

Live alerts from global media, monitored by Business Radar

New court ruling must speed up construction of Galaxy Tower, but the question is whether that will succeed

2024-02-26 (duic.nl)

New court ruling must speed up construction of Galaxy Tower, but the question is whether that will succeed

The big question hanging over the Galaxy Tower: will the tower ever be finished? It has been quiet at the dismantled construction site on Jaarbeursplein for a year now.

Read more
Van der Plas: 'Choosing certainty is a killer'

2023-10-31 (propertynl.com)

Van der Plas: 'Choosing certainty is a killer'

The approach to the housing crisis divides politics in The Hague, but they agree on one thing, as became apparent yesterday during the major Housing Debate: Rules must be 'silly'.

Read more
The future of Schiphol Airport is still quite uncertain

2023-08-25 (nrc.nl)

The future of Schiphol Airport is still quite uncertain

Aviation: The beginning of a turning point, according to Schiphol over the past six months. For example, there were hardly any queues for security during the May and summer holidays. But much is still unclear about the future of the airport.

Read more
Quarrel between Ballast Nedam and Air Products leads to mega claims on both sides

2023-07-06 (cobouw.nl)

Quarrel between Ballast Nedam and Air Products leads to mega claims on both sides

The quarrel between Air Products and Ballast Nedam about the nitrogen plant in Zuidbroek in Groningen has moved from the construction site to the courtroom. The companies are demanding amounts of up to 100 million euros from each other, according to a ruling by the Rotterdam court.

Read more
Judge considers construction of Gorcum station tunnel

2019-06-08 (bndestem.nl)

Judge considers construction of Gorcum station tunnel

The construction of the tunnel under Gorinchem station will not resume before August. The Arbitration Board for Construction has examined the conflict between ProRail and Ballast Nedam. That ruling is expected in mid-August.

Read more

Never miss a headline about Ballast Nedam Infra B.V.

Set up smart alerts with Business Radar and receive real-time updates on any new risk signal or major news story.

  • ✔️ Used by 100+ compliance teams and analysts
  • ✔️ Covers 154M+ sources in 40+ languages